China United Engineering Corporation / DONGFANG TURBINE CO., LTD. / CONSORCIO CUC-DTC
Gecelca 3: US $236 million – Gecelca 3.2: US $430 million
Synopsis
In 2008 the construction of the electric power plant Gecelca 3 in Monte líbano (located in the Córdoba department) was awarded to the CUC-DTC (Dongfang Turbine Co) consortium, with a cost of US $236 million and which was supposed to be finished in 2012.Nevertheless, repeated non-compliance have taken place, and the power plant has not begun operations, even though in 2013 the very same consortium was awarded a new tender for the construction of the electric power plant Gecelca 3.2 with a cost of US $430 million and which has not being delivered yet.

E-mail: comunicaciones@ambienteysociedad.org.co Website: www.ambienteysociedad.org.co